ADDITIONAL LOAD:

In the event a customer desires to add load to an existing service, he shall notify the District sufficiently in advance so that the District may, if economically feasible, provide the facilities required.  If the added load is considered temporary, the District will charge a Contribution-in-Aid-of-Construction (CIAC) as described in Paragraph 30, Temporary Service.  If the added load is considered permanent, the District will charge a CIAC as described in Paragraph 33, Electrical Line Extension.

Any change in voltage or a change from single phase to three phase shall be considered a line extension and Paragraph 33 shall apply. Changes from overhead secondary conductor to underground secondary cable shall be done at no charge for customers providing the conduit and back filling as described in Paragraph 33, Electrical Line Extension.

In the event that the customer fails to notify the District, and as a result District equipment is damaged, the customer shall be liable for the cost of such damage.