Available: In all territory served by the District.
Applicable: To any number of customers desiring their electric power requirements be furnished by a supplier other than the District on a "first come, first served" basis with energy requirements which, in the aggregate, are not forecast to exceed 1 megawatt annual average energy (i.e., 8,760,000 kWh) and are not provided under special contract for loads exceeding 2,500 kva.
Service Rates: $0.263 per day, plus $0.0135 per kWh for energy delivery, plus $0.0007 per kWh for ancillary services
Customer Service Policies: Service under this schedule is subject to the Customer Service Policies of the District.
Additional Requirements: The customer and customer's alternate energy supplier will be required to sign an agreement with the District setting forth criteria and responsibilities of the parties for load forecasting, scheduling, point-of-delivery on the District's distribution system and other terms and conditions applicable to this service.
In the event the customer's alternate energy supplier fails to deliver adequate energy to meet the customer's demand, the District will supply back up energy to the customer at a rate equal to the greater of the spot market price of energy at the time of the deficiency as determined by the District's market survey or the District's actual cost to supply such deficiency, in addition to the applicable delivery rate charges set forth above.
The customer agreement with the District will also set forth the customer's responsibility to reimburse the District for any additional service charges assessed by the alternate energy supplier (e.g., set-up, early termination fees, etc.) and other terms and conditions applicable to this service.
In the event a customer wishes the District to resume providing their energy supply, they will be charged $0.263 per day plus $0.0135 per KWH for energy delivery plus the most recent five year average District resource cost per KWH (currently $0.0083 per KWH) if Wells Project resource is available, and marginal cost of power if Wells Project resource is not available, for a period of six months. After six months, the customer will resume service under the appropriate General Service, Irrigation, or Street Lighting rate schedule.
Effective: First regular billing after February 1, 2004.
Adopted by Resolution No. 97-64 by Board of Commissioners dated April 7, 1997. Amended by Resolution No. 03-212 by Board of Commissioners dated December 15, 2003.