Douglas County PUD Commissioners Lynn Heminger, Ron Skagen and Jim Davis executed the following actions during the March 25, 2013 Commission meeting held at the District’s East Wenatchee Headquarters office:

Authorized change order No. 3 to contract 12-14-D, construct Douglas to Rapids 230 kV Transmission Line. Changes include reusing existing conductor on a section of the double circuit, three towers shall be removed and not reused, and removed tower foundations will be chipped out. There is no change to the not to exceed limit or completion date. (13-046)

Approved Douglas PUD’s participation in the Public Generating Pool budget for 2013.  Douglas PUD’s share of the 2013 budget is $30,000. (13-047)

Authorized  professional service agreement with Erlandsen & Associates, Inc. under contract 13-03-W, professional engineering /architectural services, Recreation Management Plan. (13-048)

Approved professional service agreement with the DOH Associates, P.S. under contract 12-29-W, architectural and engineering services for the installation of a standby diesel generator. (13-049)

Celebrated the District’s recognition as an American Public Power Association Reliable Public Power Provider (RP3). More information can be found here.

The next meeting of the Commission is scheduled for 2:00 p.m. April 1, 2013 at the District’s East Wenatchee Headquarters office.