News Release - 9/24/2012

Douglas PUD Commission Meeting Report

Douglas County PUD Commissioners Ron Skagen, Jim Davis and Lynn Heminger executed the following actions during the September 24, 2012 Commission meeting held at the District’s East Wenatchee Headquarters office:

Approved acceptance of work and final payment to Hale and Long General Contractors, Inc. under contract 12-09-D, design and build concrete communications building. All work under the contract has been completed and determined to meet the bid specifications. (12-158)

Authorized addendum No. 2 to bid 12-16-W, Expansion of Douglas Switchyard. Certain materials would have been difficult to acquire, the addendum changes some of the materials called for in the design. (12-159)

Awarded Tunnel Hill Granite of Chelan, contract 12-12-W, 2012-2013 heavy equipment services. Tunnel Hill Granite, with a bid price of $ 626,720 was the lowest responsive bidder. (12-160)

The next meeting of the Commission is scheduled for 2:00 p.m. October 1, 2012 at the District’s East Wenatchee Headquarters office.