1151 Valley Mall Parkway, East Wenatchee, WA 98802

509-884-7191 / 1-800-503-7990


Meaghan Vibbert
Public Information Officer
(509) 881-2221
News Release - 4/9/2012

Douglas PUD Commission Meeting Report

Douglas County PUD Commissioners Ron Skagen, Jim Davis and Lynn Heminger executed the following actions during the April 9, 2012 Commission meeting held at the District’s East Wenatchee Headquarters office:

Approved addendum No. 1 to bid document 12-05-D, and deliver one small single-bucket truck. This addendum clarifies items in the bid document. (12-051)

Authorized professional service agreement with Construction Special Inspection under RFQ 12-03-D, material testing services. (12-052)

Approved a call for bids under bid document 12-09-D, design and build concrete communications building. The District is in need of additional communication floor space for the Douglas County Community Network (DCCN) to meet the growing demand for co-location facilities in Douglas County. (12-053)

Authorized legal proceedings against New Day Broadband, LLC for Pole Attachment License Agreement delinquent payments. (12-054)

Approved acceptance of second year work and final payment to Tunnel Hill Granite under contract 09-23-W, 2010-2011 heavy equipment services. All work has been completed and determined to meet bid specifications. (12-055)

Authorized agreement for professional services agreement with Anchor QEA, LLC for Aquatic Settlement Work Group Chairman.  This three year agreement will not exceed $100,000. (12-056)

Approved a call for bids under bid document 12-10-W, Peninsula Park swim area improvements. These improvements are included in the 2007 Recreation Action Plan. (12-057)

The next meeting of the Commission is scheduled for 1:30 p.m. April 16, 2012 at the District’s Bridgeport office.