Douglas County PUD Commissioners Ron Skagen, Jim Davis and Lynn Heminger executed the following actions during the February 27, 2012 Commission meeting held at the District’s East Wenatchee Headquarters office:

Approved renewal of contract 10-02-D, distribution dock crew for additional one-year period with Potelco, Inc. as allowed in the contract. (12-031)

Awarded CG Power Systems Canada, Inc contract 12-01-D, supply and deliver one 230-115 kV, 200 MVA Autotransformer to Rapids Switchyard.  CG Power Systems was the lowest responsive bidder. (12-032)

Authorized purchase of an easement from Donna Marleen Witten and Noreen Daling.  Necessary for the Douglas-Rapids 230 kV transmission corridor. (12-033)

Authorized purchase of an easement from Waste Management of Washington, Inc.  Necessary for the Douglas-Rapids 230 kV transmission corridor. (12-034)

The next meeting of the Commission is scheduled for 2:00 p.m. March 5, 2012 at the District’s East Wenatchee Headquarters office.