News Release - 3/8/2010

Douglas PUD Commission Meeting Report

Douglas County PUD Commissioners Jim Davis, Lynn Heminger and Ron Skagen executed the following actions during the March 8, 2010 Commission meeting held at the East Wenatchee Headquarters office:

Authorized change order No. 14 to contract 06-41-W, generator rebuild for unit refurbishment for the Wells Hydroelectric Project.  Changes include removal of existing bushings, installation of new bushings and non-destructive examination of the runner hub. This change order will increase the not to exceed limit $46,003 bringing the total not to exceed limit to $153,913,109. (10-043)

Authorized change order No. 15 to contract 06-41-W, generator rebuild for unit refurbishment for the Wells Hydroelectric Project.  Changes include machining on the turbine shaft to allow non-destructive examination and to perform additional finite element analysis. This change order will increase the not to exceed limit $32,422 bringing the total not to exceed limit to $153,945,531. (10-044)

Authorized renewal of the Business Travel Insurance with CIGNA. (10-045)

The next meeting of the Commission is scheduled for 2:00 p.m. March 15, 2010 at the District’s East Wenatchee Headquarters office.