1151 Valley Mall Parkway, East Wenatchee, WA 98802

509-884-7191 / 1-800-503-7990


Meaghan Vibbert
Public Information Officer
(509) 881-2221
News Release - 9/12/2005

Douglas PUD Commission Meeting Report

Douglas County PUD Commissioners Mike Doneen, Jim Davis and Lynn Heminger executed the following actions during the September 12, 2005 Commission meeting held at the Bridgeport Office building:

Opened bids to provide Douglas PUD with Orondo Substation mobile modification. There were two bids received for the contract with bid prices at $88,799 and $106,300. The apparent low bid was received from Selland Construction of Wenatchee. Estimated to cost $128,628, all bids will be evaluated prior to recommendation.

Approved acceptance and final payment to ITT Pro Service of Salt Lake City, Utah under contract to provide Douglas PUD with turbine guide bearing refurbishment for the Wells Hydroelectric Project. All work under the contract has been completed and determined to meet the bid specifications. (05-219)