Douglas County PUD Commissioners Jim Davis, Lynn Heminger and Mike Doneen executed the following actions during the May 10, 2004 Commission meeting held at the Bridgeport Office building:

Awarded GDCD Electric Inc. of Wenatchee the contract to provide Douglas PUD with conduit and vault installation along Badger Mountain Road. GDCD, with a bid price of $210,480, was the lowest responsive bidder. (04-91)

Approved a call for bids to construct and install a pier, dock and floats at Columbia Cove Park in Brewster for Douglas PUD. This project is in compliance with the 1997 Recreation Action Plan Update. (04-92)

Reminded those in attendance the regular meeting scheduled for May 17, 2004 was canceled due to other Commissioner commitments. Two bid openings scheduled for that date will be conducted in public by District staff.