The following is a report of the Douglas County Public Utility District Commission meeting which was held on May 17, 1999.

The Commissioners opened bids to provide Douglas PUD with pole testing, treating and physical plant inventory for 1999. There was a single bid received for the contract. It was submitted by Osmose, Inc. of Phoenix, Arizona and was in the amount of $148,464. Estimated to cost $169,785, PUD staff will evaluate the bid and make a recommendation. Any resulting agreement is not to exceed $150,000 and will expire on November 1, 1999. It contains a provision for a one-year extension.

Four firms submitted bids to provide Douglas PUD with a new circuit breaker to be used at the Foster Creek Substation. The Commissioners opened those bids and found prices ranging from $54,883 to $59,600. The circuit breaker was estimated at a cost of $62,500. Western States Electric, Inc. of Portland, Oregon provided the apparent low bid. District staff will evaluate all bids prior to recommendation for award.

The Commissioners approved the educational sustaining membership for Douglas PUD in the Northwest Public Power Association. At the annual cost of $3,000, this NWPPA membership provides educational needs as requested by Douglas PUD and the public power industry throughout the northwest.