News Release - 5/11/2015

Douglas PUD Commission Meeting Report

​Douglas County PUD Commissioners Ron Skagen, Jim Davis and Molly Simpson executed the following actions during the May 11, 2015 Commission meeting held at the District's East Wenatchee office:

Heard a report on the May 4, 2015 bid opening for bid document 15-13-D, supply and deliver control and relay panels for Terry Substation. The apparent low bid was received from Electrical Power Products, Inc. of Des Moines, IA.

Authorized renewal of contract 14-09-D, provide traffic control services with Cascade Cable Constructors, Inc.  for an additional year as allowed by contract. This will extend the contract to June 30, 2016 and the total dollar amount will not exceed $250,000. (15-093)

Awarded contract 15-13-D, supply and deliver control and relay panels for Terry Substation to Electrical Power Products, Inc. the lowest responsive bidder. (15-094)

Approved land use permit renewal for Wells Tract 1001-01 with Jack and Connie Pitts. This permit allows commercial agricultural uses on District property. (15-095)

Approved execution of applications for bond ratings from Moody's and Standard and Poor's.  The applications are necessary to provide a rating for the District's upcoming bond refunding. (15-096)

The next meeting of the Commission is scheduled for 1:30 p.m. TUESDAY, May 26, 2015 at the District's Bridgeport office.